Home information system Information Technology Project Management 8th Edition Kathy Schwalbe
Information Technology for the Health Professions 4th Edition By Lillian Burke - Test Bank
Information Technology for the Health Professions 4th Edition By Lillian Burke - Test Bank Suggested Price: $25.00
Back to products
Test Bank For McCance & Huether’s Pathophysiology The Biologic Basis for Disease in Adults and Children 9th Edition
Test Bank For McCance & Huether’s Pathophysiology The Biologic Basis for Disease in Adults and Children 9th Edition Suggested Price: $50.00 Original price was: $50.00.$30.00Current price is: $30.00.

Information Technology Project Management 8th Edition Kathy Schwalbe

Suggested Price: $25.00

Edition: 8th Edition

Format: Downloadable ZIP File

Resource Type: Test bank

Duration: Unlimited downloads

Delivery: Instant Download

Add to wishlist
Add to wishlist
Compare
Category: information system
Share:
  • Description
  • Reviews (0)
Description

Information Technology Project Management 8th Edition Kathy Schwalbe

True / False

 

1. Suppliers are those organizations or individuals who provide procurement services.

  a. True
  b. False

 

ANSWER:   True
RATIONALE:   Feedback: Organizations or individuals who provide procurement services are referred to as suppliers. Suppliers are also known as vendors, contractors, subcontractors, or sellers.
POINTS:   1
DIFFICULTY:   Difficulty: Easy
REFERENCES:   p.466
LEARNING OBJECTIVES:   INFO.SCHW.14.86 – LO: 12-1
NATIONAL STANDARDS:   United States – BUSPROG: Analytic
TOPICS:   The Importance of Project Procurement Management
KEYWORDS:   Bloom’s: Knowledge

 

2. While outsourcing, organizations should protect strategic information because it can become vulnerable in the hands of suppliers.

  a. True
  b. False

 

ANSWER:   True
RATIONALE:   Feedback: While outsourcing, organizations should be careful to protect strategic information that could become vulnerable in the hands of suppliers.
POINTS:   1
DIFFICULTY:   Difficulty: Moderate
REFERENCES:   p.469
LEARNING OBJECTIVES:   INFO.SCHW.14.86 – LO: 12-1
NATIONAL STANDARDS:   United States – BUSPROG: Technology
TOPICS:   The Importance of Project Procurement Management
KEYWORDS:   Bloom’s: Comprehension

 

3. Project procurement management consists primarily of two processes: assessing procurements and controlling procurements.

  a. True
  b. False

 

ANSWER:   False
RATIONALE:   Feedback: There are four main processes in project procurement management. These consist of planning procurement management, conducting procurements, controlling procurements, and closing procurements.
POINTS:   1
DIFFICULTY:   Difficulty: Easy
REFERENCES:   p.470
LEARNING OBJECTIVES:   INFO.SCHW.14.86 – LO: 12-1
NATIONAL STANDARDS:   United States – BUSPROG: Technology
TOPICS:   The Importance of Project Procurement Management
KEYWORDS:   Bloom’s: Knowledge

 

4. If an organization has no need to buy any products or services from outside the organization, then it has no need to perform any of the procurement management processes.

  a. True
  b. False

 

ANSWER:   True
RATIONALE:   Feedback: Planning procurements involves identifying which project needs can best be met by using products or services outside the organization. If there is no need to buy products or services from outside the organization, then further procurement management is not needed.
POINTS:   1
DIFFICULTY:   Difficulty: Moderate
REFERENCES:   p.471
LEARNING OBJECTIVES:   INFO.SCHW.14.87 – LO: 12-2
NATIONAL STANDARDS:   United States – BUSPROG: Analytic
TOPICS:   Planning Procurement Management
KEYWORDS:   Bloom’s: Comprehension

 

5. Risk registers and stakeholder registers are outputs of the planning procurement process.

  a. True
  b. False

 

ANSWER:   False
RATIONALE:   Feedback: The risk register and the stakeholder register are inputs for the planning procurement process. Other inputs needed for planning procurements include the project management plan, requirements documentation, activity resource requirements, the project schedule, and activity cost estimates, among others.
POINTS:   1
DIFFICULTY:   Difficulty: Easy
REFERENCES:   p.471
LEARNING OBJECTIVES:   INFO.SCHW.14.87 – LO: 12-2
NATIONAL STANDARDS:   United States – BUSPROG: Technology
TOPICS:   Planning Procurement Management
KEYWORDS:   Bloom’s: Knowledge

 

6. A single contract can include all three categories of contracts.

  a. True
  b. False

 

ANSWER:   True
RATIONALE:   Feedback: Three broad categories of contracts are fixed price or lump sum, cost reimbursable, and time and material. A single contract can include all three of these categories if it makes sense for a particular procurement.
POINTS:   1
DIFFICULTY:   Difficulty: Easy
REFERENCES:   p.471-472
LEARNING OBJECTIVES:   INFO.SCHW.14.87 – LO: 12-2
NATIONAL STANDARDS:   United States – BUSPROG: Technology
TOPICS:   Planning Procurement Management
KEYWORDS:   Bloom’s: Knowledge

 

7. Indirect costs are those costs can be traced back to a project in a cost-effective way.

  a. True
  b. False

 

ANSWER:   False
RATIONALE:   Feedback: Indirect costs are not directly related to the products or services of the project, but they are indirectly related to performing the project. Normally, these costs cannot be traced back to the project in a cost-effective way.
POINTS:   1
DIFFICULTY:   Difficulty: Moderate
REFERENCES:   p.472-473
LEARNING OBJECTIVES:   INFO.SCHW.14.87 – LO: 12-2
NATIONAL STANDARDS:   United States – BUSPROG: Analytic
TOPICS:   Planning Procurement Management
KEYWORDS:   Bloom’s: Comprehension

 

8. Buyers absorb lesser risk with cost-reimbursable contracts than they do with fixed-price contracts.

  a. True
  b. False

 

ANSWER:   False
RATIONALE:   Feedback: Cost-reimbursable contracts often include fees, such as a profit percentage or incentives for meeting or exceeding selected project objectives. Buyer absorb more of the risk with cost-reimbursable contracts than they do with fixed-price contracts.
POINTS:   1
DIFFICULTY:   Difficulty: Moderate
REFERENCES:   p.473
LEARNING OBJECTIVES:   INFO.SCHW.14.87 – LO: 12-2
NATIONAL STANDARDS:   United States – BUSPROG: Analytic
TOPICS:   Planning Procurement Management
KEYWORDS:   Bloom’s: Comprehension

 

9. The fee in a CPFF contract constantly varies even when the scope of a contract remains the same.

  a. True
  b. False

 

ANSWER:   False
RATIONALE:   Feedback: With a cost plus fixed fee (CPFF) contract, the buyer pays the supplier for allowable performance costs plus a fixed fee payment that is usually based on a percentage of estimated costs. This fee does not vary, however, unless the scope of the contract changes.
POINTS:   1
DIFFICULTY:   Difficulty: Moderate
REFERENCES:   p.474
LEARNING OBJECTIVES:   INFO.SCHW.14.87 – LO: 12-2
NATIONAL STANDARDS:   United States – BUSPROG: Analytic
TOPICS:   Planning Procurement Management
KEYWORDS:   Bloom’s: Comprehension

 

10. In unit pricing, the total value of the contract is a function of the quantities needed to complete the work.

  a. True
  b. False

 

ANSWER:   True
RATIONALE:   Feedback: Unit pricing can be used in various types of contracts to require the buyer to pay the supplier a predetermined amount per unit of product or service. The total value of the contract is a function of the quantities needed to complete the work.
POINTS:   1
DIFFICULTY:   Difficulty: Moderate
REFERENCES:   p.474
LEARNING OBJECTIVES:   INFO.SCHW.14.87 – LO: 12-2
NATIONAL STANDARDS:   United States – BUSPROG: Technology
TOPICS:   Planning Procurement Management
KEYWORDS:   Bloom’s: Comprehension

 

11. All contracts should include specific clauses that take into account issues unique to the project.

  a. True
  b. False

 

ANSWER:   True
RATIONALE:   Feedback: Any type of contract should include specific clauses that take into account issues unique to the project.
POINTS:   1
DIFFICULTY:   Difficulty: Easy
REFERENCES:   p.474
LEARNING OBJECTIVES:   INFO.SCHW.14.87 – LO: 12-2
NATIONAL STANDARDS:   United States – BUSPROG: Technology
TOPICS:   Planning Procurement Management
KEYWORDS:   Bloom’s: Knowledge

Related

Reviews (0)

Reviews

There are no reviews yet.

Be the first to review “Information Technology Project Management 8th Edition Kathy Schwalbe” Cancel reply

Your email address will not be published. Required fields are marked *

1 of 5 stars 2 of 5 stars 3 of 5 stars 4 of 5 stars 5 of 5 stars

Related products

Add to cart
Quick view
Compare
Add to wishlist

INFORMATION SYSTEMS TODAY MANAGING THE DIGITAL WORLD, 8E JOSEPH – TEST BANK

information system
Suggested Price: $25.00 Compare
Add to cart
Quick view
Compare
Add to wishlist

Information Technology Auditing 4th Edition By James A.Hall – Test Bank

information system
Suggested Price: $25.00 Compare
Add to cart
Quick view
Compare
Add to wishlist

Information Systems Today 7th Edition by Valacich – Test Bank

information system
Suggested Price: $25.00 Compare
Add to cart
Quick view
Compare
Add to wishlist

Information Technology Auditing 4e James A Hall

information system
Suggested Price: $25.00 Compare
Add to cart
Quick view
Compare
Add to wishlist

Information Technology For Managers 2nd Edition By by George Reynolds – Test Bank

information system
Suggested Price: $25.00 Compare

Nursingtestbankltd

  • 100 E San Fernando St, San Jose, CA 95112, United States
  • Whatsapp: +1-6269466008
  • Email: Nursingtestbankltd@gmail.com

Useful links
  • FAQs
  • Privacy Policy
  • Terms & Conditions
  • Contact Us
Categories
  • Nursing Test Bank
  • NCLEX Exam
Pages
  • Home
  • Nursing Test Bank
  • Exams
    • NCLEX Exam
    • Ati Exams
  • Blog
Recent post
  • Digitization of Test Banks in the 21st Century
  • Nursing Test Bank: The Guide to Excellence
Nursingtestbankltd
payments
  • Menu
  • Categories
  • Nursing Test Bank
  • NCLEX Exam
  • Home
  • Nursing Test Bank
  • Exams
    • NCLEX Exam
    • Ati Exams
  • Blog
  • Wishlist
  • Login / Register
Shopping cart
Close
Sign in
Close

Lost your password?

No account yet?

Create an Account
Start typing to see products you are looking for.
Shop
Wishlist
1 item Cart
My account

Do you need any help?